S-01Construction UpdatesNef Arsa
Nef Arsa Biga Çeşmealtı – Construction Site Updates

Work is progressing at full speed.
- 53% of the wastewater infrastructure has been completed.
- 55% of the ground preparation and road embankment works have been completed.
- Connection lines for the wastewater network have been installed and sealed with end caps. Wastewater connection points for the individual plots have also been completed.


